2020 Pavement Management: Project to mill and overlay City streets begins in September

2020 pavement management

COMPLETED

Sept. 8, 2020 | Public Information Office

Beginning September 15th, crews will re-pave streets throughout the community. The City Commission approved an increase of funding in the 2020 budget to help Leavenworth’s roads to $1.8 million - more than double in previous years. This decision was made after feedback from the public about road conditions and a contractor did imaging of the streets in 2016 and 2019 that showed deterioration. These streets were selected for mill and overlay, which means removing a portion of the road and overlaying with asphalt. The mill and overlay projects are scheduled for September and October. All work is weather dependent.

  • Pawnee Street from 16th Street to the creek
  • 19th Street from Ottawa Street to Osage Street
  • Miami Street and Michael Street west of 17th Street
  • Terry Street from 16th to 17th
  • Cherokee Street from 20th to 15th
  • 20th Street from Choctaw to Spruce
  • 20th Street from Metropolitan Avenue to Ottawa
  • Cheyenne Street from 7th to Broadway
  • Pawnee Lane cul-de-sac
  • 10th Street from Pawnee to Shawnee Street
  • Kiowa Street from 10th Street to Broadway Street
  • Ottawa Street from 10th Street to 7th Street
  • Shawnee Street from 10th Street to bridge
  • Ottawa Street from 4th to 2nd Street
  • Pottawatomie Street from Broadway to Esplanade Street
  • Osage Street from Broadway to Esplanade Street
  • 5th Street from Osage to Shawnee Street
  • Miami Street from 7th Street to 5th Street
  • Shawnee Street from Broadway to 5th Street
  • Estates Street from 21st Street to 20th Street

Alternates:

  • Tonganoxie Drive from Shenandoah Street to Candlewood Drive