Work for the City of Leavenworth’s pavement management program is scheduled to begin in August. The 2023 budget invests $1.8 million into major repairs of city streets.
Work includes three phases:
- Mill and overlay, in which 2” of driving surface is scraped away or “milled” from the road and replaced with a 2-inch asphalt overlay
- Crack sealing and microsurfacing, in which thin surface material is added to the top of the driving surface
- Replacement of one City-owned parking lot is done each year. In 2022, the City replaced and repaired the Leavenworth Public Library parking lot. In 2023, the lot scheduled for replacement is on the east side of City Hall. Work will include tearing out concrete and adding new storm drainage, landscaping and repaving lot.
The following streets include a 2-inch full-width mill with a 2-inch asphalt overlay of existing pavement:
- Poplar Street (east of 3rd Street to 2nd Street)
- Spruce Street (4th Street to west of 3rd Street)
- Shawnee Street (15th Street to 10th Street)
- 10th Avenue (Michigan Street to Stockton Street)
- Vilas Street and 15th Street Intersection
- 3rd Street and Arch Street Intersection (regrade manhole only)
- N. 7th Street (Kiowa Street to Alley North of Dakota Street)
These streets will receive crack sealing and microsurfacing:
- High Street (15th Street to Grand Avenue)
- Olive Street (Casey Court to Grand Avenue)
- Newman Street (Spruce Street to High Street)
- 3rd Street (Linn Street to Spruce Street)
- Columbia Avenue (Frank Street to Spruce Street)
- Columbia Avenue (Michigan Street to Ohio Street)
- Ohio Street (Western Street to Stoneleigh Court.)
- Ottawa Street (13th Terrace to 12th Street)
- Dakota Street (2109 W. Dakota to 20th Street)
- Muncie Court (Muncie Road to Cul-de-sac)
- Lincoln Court (Richmond Drive to Dixie Drive)
- Garland Avenue (Village Street to Deerfield Street)
- Village Street (Cul-de-sac to Broadway Terrace)
- Parkway Drive (Muncie Road to Dead End)
- 8th Street (Dakota Street to Metropolitan Avenue)
- Kingman Street (Ohio Street to Kansas Street)
- Quincy Street (Washington Street to Grand Avenue)
- Pennsylvania Street (Klemp Street to 10th Avenue)
- 21st Street (High Street to Shawnee Street)
- Choctaw Street (21st Street to 20th Street)
- Randolph Court (Cul-de-sac to 17th Street)